March 2020 QUARTERLY ACTIVITY REPORT
30 April 2020
SUMMARY
Local RC drilling contractors, R.Munoz Perforaciones, awarded contract for
percussion drilling in the Elevado regional targets
Completed prospecting activities on the Elevado regional stream sediment survey and
regional prospecting (quadbike) surveys
Completed RC drilling programme, 8 holes drilled (1338m) over 4 target areas
Demobilised Emu’s employees and contractors from project
Site rehabilitation requirements completed
EMU announced it would exit Elevado given the lack of significant gold values from
assays during the 2019/2020 season
EMU commenced project wind up activities and mitigation of costs
EMU commenced a cost review in response to potential COVID 19 impacts
EMU CEO and Senior Geologist attended the Toronto PDAC convention securing a
list of potential new projects
Project Generation activity accelerated during the quarter and a long list of potential
projects was prepared
A review of the 8 Mile Dam Project in WA was undertaken
ELEVADO PROJECT, CHILE
During the quarter, EMU focused on the RC drilling phase of the regional drilling programme of the
overall 2019/2020 campaign. After the completion of the Synergy Drilling DDH (Diamond Drilling)
drilling phase on 31 December 2019, the final preparations and implementation of the R.Munoz
Perforaciones RC drilling programme were actioned for commencement in mid-January 2020. This
programme was planned to test the priority regional anomalies outlined in the various regional
tenements and prospects outside of the main Vidalita tenements. EMU completed this Stage 2 drilling
programme during the quarter.
Activities during the quarter were as follows:
RC drilling contract awarded to R.Munoz Perforciones. The RC Rig was mobilised to Elevado
on 15 January 2020m and commenced drilling on 20 January 2020. A total of 8 holes (1338m)
was drilled at 4 regional prospects (Peon, Jotahues, Jotahues Norte, Arroyo Ancho). The
programme was completed on 23 February 2020, and the drilling contractors were
demobilised by 28 February 2020.
WWW.EMUNL.COM.AU • ASX: EMU
Page 1 of 5
EMU NL
March 2020 QUARTERLY ACTIVITY REPORT
30 April 2020
EMU finalised its prospecting, stream sediment surveys and regional exploration programme
during the period.
As assay results from previous seasons’ aircore drilling and those from the current season’s
diamond and RC drilling failed to produce results sufficiently significant to justify follow up,
results, EMU decided to exit the Elevado Project and terminate the Vidalita Option Agreement
(SLM Vidalita del Rio Vidal Gormaz) and greater Elevado tenement package (BLC SpA and
Prospex SpA). (See ASX Announcement – Letter to Shareholders 17 March 2020)
EMU completed the rehabilitation of drill sites and camp area and all EMU staff and external
contractors were demobilised by 3 March 2020.
A full assessment of drilling results was completed with the finalisation of all outstanding
ALS drilling geochemistry. Disappointingly no positively significant gold assay results from
this season’s drilling campaign were achieved; ASX Announcements 22 and 23 April 2020.
Figure 1 below shows the diamond drill hole (DDH) locations which were drilled during the previous
quarter as well as the four new target areas tested with RC drilling during the current quarter.
Figure 1: Location of RC target areas and DDH targets drill tested during 2020 Q1
WWW.EMUNL.COM.AU • ASX: EMU
Page 2 of 5
EMU NL
March 2020 QUARTERLY ACTIVITY REPORT
30 April 2020
CORPORATE
COVID 19
EMU embarked on a cost savings regime following the evolution of the pandemic and the responses
of various governments and authorities within the jurisdictions it operates. EMU reduced its cost
exposure following its decision to exit Elevado. During the quarter there were no material impacts
to EMU’s business. EMU developed “work from home” procedures and more fully utilised modern
technologies for its communications.
Project Generation
EMU continued its efforts in identifying and reviewing resource and exploration projects both within
Australia and overseas with a view to acquiring an asset, or assets, that may have the potential to add
significant financial value and returns for its shareholders. EMU’s CEO, and its senior geologist,
attended the Toronto PDAC convention over the period 1-4 March. Numerous project opportunities
were identified for follow up.
EMU maintains a strict criterion in its evaluation of these projects. The focus of evaluation of
opportunities is not limited to greenfield exploration. EMU’s evaluation criteria include projects that
have the potential to be value-accretive and demonstrate significant upside at any stage in the project
life cycle including greenfield exploration, late-stage exploration and near-term cash flow. EMU
prepared a long list of approximately 30 projects which are under evaluation.
A key focus of the board following the exit from Elevado has been to target Australian gold projects
in the first instance.
Other Work
During the quarter, the EMU team prioritised finalising all activities at Elevado. It also worked on
reviewing EMU’s Western Australian tenement (under application). The 8 Mile Dam Project, near
Menzies, was subject to a desktop review by the geology team.
Other Disclosures
Appendix 5B
Item 6.1 in the Appendix 5B lodged concurrently with this Quarterly Activities Report includes
aggregate amounts paid to directors for directors’ fees, related statutory superannuation and office
rent of $4,250 per month (net of GST) plus variable outgoings paid to a director.
ASX Waiver – Approval to issue shares
As all tenements in Chile subject of the agreement with Prospex SpA and BLC SpA were dropped
effective 1 April 2020, EMU has no further commitment to issue Consideration Shares as defined
within the terms of the ASX waiver (refer to the December 2019 quarterly activity report, released
on 29 January 2020, for further details).
RELEASE AUTHORISED BY THE BOARD
Contact Details: Doug Grewar - CEO – Office: +61 8 9226 4266; Mobile: 0419 833 604
WWW.EMUNL.COM.AU • ASX: EMU
Page 3 of 5
EMU NL
March 2020 QUARTERLY ACTIVITY REPORT
30 April 2020
Table 1: Schedule of Tenements as at 31 March 2020 – Elevado Project, Atacama Region, Chile
Concession ID
Type
Description/Status
Vidalita A2
Vidalita B2
Vidalita C2
Vidalita D2
Vidalita E2
Vidalita F2
Vidalita A1 1/60
Vidalita B1 1/60
Vidalita C1 1/60
Vidalita D1 1/60
Vidalita E1 1/36
Vidalita F1 1/40
Vidalota A
Vidalota A1 AL 18
Vidalota B
Vidalota B1 AL 20
Vidalota C
Vidalota D
Vidalota E
Peon 1 – 16
Ciclope Tuerto 1 - 9
Tierra 1 – 15
Exploration
Exploration
Exploration
Exploration
Exploration
Exploration
Mining
Mining
Mining
Mining
Mining
Mining
Exploration
Mining
Exploration
Mining
Exploration
Exploration
Exploration
Exploration
Exploration
Exploration
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (Prospex/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Option to acquire 100% (BLC/Emu Option Agreement)
Emu 100%
Table 2: Schedule of Tenements as at 31 March 2020 – Western Australia
Concession ID
E29/1080
Type
Exploration
Description/Status
Emu 100% - Application
WWW.EMUNL.COM.AU • ASX: EMU
Page 4 of 5
EMU NL
March 2020 QUARTERLY ACTIVITY REPORT
30 April 2020
Emu NL
ABN 50 127 291 927
COMPETENT PERSON’S STATEMENT
ASX Codes: EMU and EMUCA
Any details contained herein that pertain to exploration
results, mineral resources or mineral reserves are based
upon information compiled by Mr Francisco Montes,
Senior Geologist and Exploration Manager - Chile, of
Emu NL. Mr Montes is a Member of the Australasian
Institute of Geoscientists and has sufficient experience
in the activity which he is undertaking to qualify as a
Competent Person as defined in the 2012 edition of the
“Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves” (JORC
Code). Mr Montes consents to the inclusion herein of
the matters based upon his information in the form and
context in which it appears.
10 Walker Ave
West Perth, WA 6005
T +61 8 9226 4266
E info@emunl.com.au
PO Box 1112
West Perth, WA 6872
Fully paid shares (listed)
298,005,436 (including 15.7m which EMU
can buy back for nil consideration)
Contributing Shares (listed)
33,725,496 paid to $0.03, $0.03 to pay, no
call before 31/12/2023
Options (unlisted)
65,759,750 options to acquire partly paid
shares, exercisable at $0.02 each, on or
before 21 December 2020
84,355,000 options to acquire fully paid
shares, exercisable at $0.20 each, on or
before 15 January 2021
8,454,468 options to acquire fully paid
shares, exercisable at $0.20 each, on or
before 16 January 2021
12,000,000 options to acquire partly paid
shares, exercisable at $0.03 each, on or
before 21 December 2021
Directors:
Peter Thomas
Non-Executive Chairman
Terry Streeter
Non-Executive Director
Gavin Rutherford
Non-Executive Director
Tim Staermose
Non-Executive Director
Investor enquiries:
FORWARD LOOKING STATEMENTS
As a result of a variety of risks, uncertainties and other
factors, actual events and results may differ materially
from any forward looking and other statements herein
not purporting to be of historical fact. Any statements
concerning mining reserves, resources and exploration
results are forward looking in that they involve
estimates based on assumptions. Forward looking
statements are based on management’s beliefs, opinions
and estimates as of the respective dates they are made.
The Company does not assume any obligation to update
forward looking statements even where beliefs,
opinions and estimates change or should do so given
changed circumstances and developments.
T +61 8 9226 4266
E info@emunl.com.au
WWW.EMUNL.COM.AU • ASX: EMU
Page 5 of 5