Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
QUARTERLY ACTIVITY REPORT
3 MONTHS ENDED 31 December 2023
EMU’s explora on ac vity focus during the quarter centred on the Georgetown Project in North
Queensland. A second, follow up, reconnaissance field programme was conducted during late
October – early December 2023. The Georgetown Project has emerged as a priority project for
EMU as Rare Earth projects, par cularly clay hosted projects, have progressively lost investor
and market interest.
At its Annual General Mee ng, held in November 2023, the fickle nature of REE investment was
discussed. EMU has commenced the priori sa on of its work at the Georgetown Project, and
the winding down of expenditures at its REE projects in WA despite the comple on of excellent
programmes of explora on work at all REE projects resul ng in significant TREO1 grades.
The Georgetown Project offers early-stage explora on over very prospec ve ground with
poten al for scale deposits to be discovered. More than 1,000 mineral occurrences have been
reported from historic mining and prospect areas. EMU’s early work at Georgetown has been
and is focussed on the defini on of prospects that may have the poten al to evolve into scale
mining opera ons.
The two reconnaissance field trips conducted during 2023 in August and December, resulted in
the collec on of 978 rock, stream, termite mound and soil samples. Par al assay results from
the sampling have provided significant encouragement. Success has been achieved with the
discovery of a high-grade copper vein swarm within the northern Fiery Creek tenement,
poin ng to poten al early, scale explora on success. High grade copper, gold, lead, and silver
results have been recorded from a number of iden fied prospec ve areas with further assay
results awaited. Anomalous pathfinder elements at prospects located at all 3 tenements, have
also provided further encouragement for follow up work.
GEORGETOWN PROJECT
EMU completed its maiden 15-day reconnaissance field survey during July and August 2023.
A substan al high grade, outcropping, copper in quartz veining, (poten ally polymetallic)
system was iden fied within the Fiery Creek tenement with assay results from in situ rock
sampling evidencing broad, high-grade copper and silver mineralisa on.
EMU updated the market with its results following this field trip2.
1
2
Assays results record up to 18% copper (180,100ppm) and up to 6.4 ounces silver (200
g/t) from rock samples in broad quartz breccia hosted veins at Fiery Creek.
Extensive 750m x 750m intrusive related, north-south striking, outcropping copper
veining up to 2m wide identified from field mapping.
Veining displays extensive secondary copper mineralisation at surface.
Total Rare Earth Oxides
ASX Release “Copper Silver Lead Assay Results Pegmatite Fields Georgetown” 5 October 2023
ABN 50 127 291 927 | 10 Walker Avenue, West Perth, WA, 6005 | PO Box 1112, West
Perth, WA, 6872 E: info@emunl.com.au | www.emunl.com.au | ASX Code: EMU
Multi element assay results indicate the possibility of a significant copper dominant,
polymetallic system with pathfinder element anomalism widespread throughout the
sampled area.
EMU posits a further ~2km strike of the copper-silver mineralisation extending to the
south.
Assays from rock chip samples report up to 35.4 ounces per tonne (1,100 g/t) silver
and 26% (261,000ppm) lead from Snake Creek prospect area.
Extensive pegmatite veining up to 50m wide and striking approximately 2km observed
within Fiery Creek and the Perpendicular Peak tenements.
Fiery Creek Copper Veining
In the central zone of a circular geophysics anomaly known as the Yataga Granodiorite, within
the Fiery Creek tenement, the explora on team discovered swarms of north-south trending,
subver cal quartz breccia veins with extensive secondary copper mineralisa on including
malachite, chrysocolla, azurite, covellite and chalcocite. These outcropping veins were
observed to be up to 2m wide and were able to be followed along-strike for hundreds of
metres.
The veins are cut by east-west trending faults. Sca ered small pits and rock piles indicate
historical workings in the area. No record of modern explora on has been published and none
is thought to have been undertaken.
The mineralised veining was noted to be rich in oxides and sulphides, coinciding with natural
clearings in the vegeta on, indica ng that the shedding sulphides within the immediate vein
areas are preven ng plant growth. These visible, linear, cleared areas, which can be
determined from satellite imagery as open ground, free from vegeta on, provide EMU with
strong vectors for follow up work.
EMU’s field team collected samples from surface rocks, termite mounds and stream
sediments. These samples were returned to Labwest in Perth with assay results confirming a
copper-rich (polymetallic) prospect with grades of up to 18% copper and 6.4 ounces per tonne
of silver.
During the second field trip in December 2023, samples were collected in the southern area
of the outcropping copper veining at Fiery Creek with assays results pending. Library samples
of the rock have been dispatched for third party petrography follow up to determine
mineralisa on characteris cs which will provide further targe ng informa on.
Page | 2
Figure 1. Aeromagnetic map of prominent Yataga Granitoid intrusive feature with sample area
marked in red and EMU’s review of vegetation destruction indicating extensions of copper -silver
rich veining.
Snake Creek Lead-Silver
Evidence of historic workings were observed at Snake Creek. Shallow trenches were observed,
aligned along an east - west trending shear zone in a rhyoli c host rock. Fresh veins of
sulphides were seen in the ore, including pyrite and galena. Altera on around these shear
zones was primarily chlori c, with some possible silica flushing indica ng quartz with
extensive iron oxide and boxworks a er sulphides. Some narrow stockwork quartz veining
was also iden fied in the area.
The historic workings were noted to be up to 2m wide. Assay results from samples taken
during the survey from the area report lead values up to 26.1% and silver values up to 35.4
ounces per tonne, (1,100 grams per tonne). The field survey has provided encouragement for
the targe ng of poten al scale project. EMU has commenced further work to verify the
significance of this mineralisa on.
Page | 3
Muni ons Creek Prospect
The Muni ons Creek area was iden fied as a priority during the pre-fieldwork, with historic rock
chip samples repor ng significant gold values3. The gold-hos ng structure was observed to be a
3-4m wide blue-grey quartz vein with a fine, brecciated fracture network. The vein strikes NE-SW
and is roughly sub-ver cal to steeply dipping towards the east. The 200m strike, mul ple vein
occurrence suggests a stacked vein system. EMU has since commenced new work to ascertain
the poten al scale of the prospect.
Pegma
es
A pegma te swarm was mapped in the south of the Fiery Creek tenement. The pegma tes
were between 5m-50m wide and were con nuous, cross faulted, and extended up to 1.9
kilometers in strike. They trend east-west and are subver cal. The pegma tes show some
displacement along north-south trending faults and were observed to contain large mica balls
up to 20cm across, are variably potassic and o en show graphic textures. The pegma tes
were very coarse grained with an abundance of micas and feldspars observed.
Some east-west trending pegma c veins were also found at Muni ons Creek prospect and
were sampled. These were similar in character to those found in Fiery Creek.
GEORGETOWN GOLD4
At its Sandy Creek area in the Georgetown tenement, EMU recorded gold grades of up to
36.1g/t from rock samples. Sandy creek is situated close to the historic gold mining town of
Georgetown. The area is marked by a significant number of old workings and presents EMU
with an excellent follow up target prospect. EMU’s rock samples, obtained from the Dagworth
prospect, recorded up to 15.4g/t. EMU conducted a review of historic informa on recorded
from its Georgetown Project tenements which was presented in its 7 December ASX release.
Camp Oven Creek area historic surface rock assay results ranging from 12.9 up to 224
g/t gold and 24 to 135 g/t silver from rock samples in broad rhyolite breccia hosted
veins in the NW5.
15 historic rock values greater than 31.1 g/t gold (> 1 Ounce) iden fied from zones in
the Camp Oven Creek, 130 Quartz Vein and Quartz 250 Prospects (“new historic
informa on”)6.
Three historic rock samples in the Quartz 130 prospect returned values ranging from
51 g/t gold up to 73 g/t gold7.
3
ASX Release “Scale Project Added to Exploration Portfolio” 1 September 2022
ASX Release “EMU Records Gold Assays to 36.1 g/t at Georgetown QLD” 7 December 2023
5
GSQ Open Data Portal (https://geoscience.data.qld.gov.au) Company Report CR20472 (Emu Appendix 1 –
CR20472 Appendix 3). Table 4.
6 GSQ Open Data Portal (https://geoscience.data.qld.gov.au) Company Reports 20472, 23854, 71155. Also see
table 4. Described as “new” in the sense that knowledge of this information is new to EMU.
7
GSQ Open Data Portal (https://geoscience.data.qld.gov.au) Company Report 23854, 71155. Also see table 4.
4
Page | 4
Limited historic drilling at Rhyolite Breccia/Turtle Arm returned values to 2m at
15.8g/t Au and 3m at 2.8g/t Au.
86 historic surface rock samples greater than 1 g/t gold with a weighted average of
17.3 g/t within Georgetown EPM 27667 - NW Camp Oven Creek/Turtle Arm
quadrant8.
2 EMU Reconnaissance rock samples returned 36.1 g/t gold and 25.6 g/t gold
respec vely from the Sandy Creek prospect just south of Georgetown.
Limited historic drilling at Muni ons Creek (EPM 27642) returned values to 4m at
2.73/t Au and 1m at 10.85g/t Au.
8
GSQ Open Data Portal (https://geoscience.data.qld.gov.au) Company Reports 20472, 21962, 23854, 28639,
42618, 71155. Table 4.
Page | 5
Figure 2 - Iden fied current and historic Gold Occurrences at Fiery Creek and Georgetown Tenements
Page | 6
CONDINGUP REE PROJECT
Assays results from EMU’s maiden aircore drilling programme were received from
Condingup REE Project during the quarter ending 31 December 2023. This first pass, 34
hole 2,2762m aircore drilling programme, was highly successful with all holes repor ng
REE TREO grades up to 2,513ppm TREO. This result confirms EMU’s credible endeavour
to meet market aspira ons and investor expecta on to search for and acquire clay hosted
REE projects. In its release to the market, following the drilling, EMU highlighted9
Extensive high grade assay results recorded from standard 4m composite samples up
to 2,513pmm Total Rare Earth Oxides (TREO).
High value Magnetic Rare Earth Oxide (MREO) ratio to TREO of 21% (average for
drilling programme) extending to a maximum of 40.7% at Merivale Rd.
Heavy Rare Earth (HREO) ratio of up to 53.08%.
The aircore programme targeted only a minor portion of viable clay trap sites and
deeply weathered Booanya granites within the 1,560 square kilometre project,
indicating the vast scale of prospectivity available for further testing.
First phase aircore drilling programme demonstrated continuity of grade and
thickness over multiple kilometres in the wide-spaced drill programme with
mineralised lenses running up 6-8kms in length.
Anomalous grade >300ppm TREO values intersected in 33 of the 34 holes drilled over
significant intercepts up to a maximum 59m vertical drill intercept.
High grade >750ppm TREO values intersected in 67% of holes drilled. Flat-lying REE
zones located in relatively shallow thick clay zones immediately above fresh granite
lithologies.
The “proof of concept” roadside aircore drilling programme tested three main targets at KettlesParmango, Merivale and Baring Roads where interpreted bedrock mapping indicated deep clay
traps within the prospective Booanya Suite granitic intrusives. The three drill targets were tested
by continuous 4m composite sampling through the complete weathering profile from surface to
bedrock. Overall, the drilling tested only a very small proportion of the substantial 1,560 square
kilometre Condingup REE Project, leaving scope for multiple target areas remaining for followup work. (see Figure 3– Drill Collar Location Plan).
9
ASX Release “Extensive High Grade REEs over multiple km at Condingup Project” 9 October 2023
Page | 7
Figure 3 –Drill Collar Plan showing positions relative to geology and Emu tenement boundaries
The Condingup aircore drilling programme and mul element analysis of the sampling
confirmed significant grades of REE mineralisa on over wide intercepts in this “first pass”
drilling programme designed to test the proof of concept.
The assay results returned anomalous grade >300ppm TREO values in 33 of the 34 holes
completed, demonstra ng the prospec vity of the region and the fer lity of the host rocks.
Consistent wide mineralised intercepts confirmed the Condingup REE Project as a project that
stands “head-to-head” alongside its peers in the emerging globally significant Esperance clay
hosted REE province.
The distribu on of anomalous REE elements generally occupy a variable but wide interval of
clays and saprolite immediately above the granite bedrock. The width of intercepts in the
ver cal drilling range up to 59m (Hole 23CAC019) and the lateral extensions of these “lenses”
reach at least 6-8km, which points to significant project prospec vity and economics.
BADJA GOLD/TUNGSTEN/LITHIUM PROJECT
EMU has received several approaches from interested par es. EMU is evalua ng the interest
looking to realise maximum value for the asset either through sale or reten on. EMU’s work
at Badja has defined and upgraded a mul -element project adding prospec vity for high
grade gold, tungsten, and lithium.
Page | 8
VIPER GRACELAND AND MERREDIN REE PROJECTS
EMU conducted no further work other than the onerous administra ve requirements to
retaining these projects.
SUNFIRE PROJECT
EMU has no further updates to report on the Sunfire Project as it awaits direc on from the
WA Government as to its inten on to allow drilling ac vi es in the old forestry workings in
the state forest. EMU has not received any feedback from its correspondence most recently
dated November 2022.
As stated in the previous quarterly, Emu has met all required environmental obliga ons with
respect to accessing WA State Forest areas within the project with the commencement of
onsite explora on ac vi es. There con nues to be a complete lack of progress coupled with
the absence of any indica on from Government departments as to the likely probability of
drilling consent being forthcoming. This lack of progress and inability by the Government
departments to determine the viability of ongoing explora on and drill tes ng of the Sunfire
Ni-Cu targets has frustrated explora on that would have been in the interest of the State and
its peoples. EMU has placed progress on the back burner to allow Governmental
instrumentali es to respond at their glacial pace.
NEW OPPORTUNITIES
EMU con nues to assess asset acquisi on opportuni es globally. The Company looks at, and
screens corporate opportuni es as they are presented.
RELEASE AUTHORISED BY THE BOARD
For further informa on, please contact:
Doug Grewar
Chief Execu ve Officer
Mobile: 0419 833 604
info@emunl.com.au
Investors can sign into our interac ve investor hub and join in on the conversa on with Emu
NL.
h ps://investorhub.emunl.com.au/auth/signup
EMU Investorhub QR Code
Page | 9
Tenement Schedule (Status as at 31 December 2023)
Tenement ID
(DMIRS ID)
Project
Type
Descrip on/ Status
M59/739 – Gnows Nest
E59/2315 – Gnows Nest
Badja
Badja
Mining
Explora on
EMU 100% - Granted
EMU 100% - Granted -
P59/2068 – Monte Cristo
Badja
Prospect
EMU 100% - Granted
P59/2071 – Monte Cristo
Badja
Prospect
EMU 100% - Granted
P59/2072 – Monte Cristo
Badja
Prospect
EMU 100% - Granted
P59/2073 – Monte Cristo
Badja
Prospect
EMU 100% - Granted
P59/2074 – Monte Cristo
Badja
Prospect
EMU 100% - Granted
E59/2495 – Warramboo
Badja
Explora on
EMU 100% - Granted
E59/2817 - Warramboo
Badja
Explora on
EMU 100% - Pending
E70/5507 – Sunfire
Sunfire
Explora on
EMU 100% - Granted
E70/5346 – Sunfire
Sunfire
Explora on
EMU 100% - Granted
E70/5146 - Graceland
Graceland
Explora on
EMU 100% - Granted
E70/5603 – Roe
Graceland
Explora on
EMU 100% - Granted
E70/6066 – Roe
Graceland
Explora on
EMU 100% - Granted
E70/5155 – Viper
Viper
Explora on
EMU 100% - Granted
E70/5602 – Kent
Viper
Explora on
EMU 100% - Granted
E70/6430 – Kent
Viper
Explora on
EMU 100% - Granted
Condingup
Condingup
Condingup
Condingup
Condingup
Condingup
Condingup
Merredin
Balladonia
Balladonia
Condingup
Condingup
Condingup
Merredin
Merredin
Badja
Merredin
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
Explora on
EMU 100% - Granted
EMU 100% - Granted
EMU 100% - Granted
EMU 100% - Granted
EMU 100% - Granted
EMU 100% - Granted
EMU 100% - Granted
EMU 100% - Pending
EMU 100% - Pending
EMU 100% - Pending
EMU 100% - Granted
EMU 100% - Granted
EMU 100% - Granted
EMU 100% - Pending
EMU 100% - Pending
EMU 100% - Granted
EMU 100% - Pending
E63/2277 - Neridup
E63/2278 - Neridup
E63/2295 - Neridup
E63/2296 - Neridup
E63/2304 - Neridup
E63/2305 - Neridup
E69/4116 - Neridup
E70/6300 – Avon
E69/4117 - Balladonia
E69/4118 - Balladonia
E63/2326 - Neridup
E69/4146 - Neridup
E63/2342 - Neridup
E70/6434 – Nelson
E70/6436 - Nelson
E59/2836 - Warramboo
E70/6513 - Avon
Page | 10
Emu NL
ABN 50 127 291 927
ASX Codes: EMU and EMUCA
10 Walker Ave
West Perth, WA 6005
T +61 8 9226 4266
E info@emunl.com.au
PO Box 1112
West Perth, WA 6872
Fully paid shares (listed)
2,024,771,286 (including 18.6m the
subject of the ATM which EMU can buy
back for nil consideration)
Contributing Shares (listed)
40,485,069 paid to $0.03, $0.03 to pay,
no call before 31 December 2023
Contributing Shares (Unlisted)
35,000,000 paid to $0.0001, $0.04 to
pay, no call before 31 December 2025
Options (unlisted)
172,453,621 options to acquire fully paid
shares, exercisable at $0.01 each, on or
before 7 October 2024
317,375,004 options to acquire fully paid
shares, exercisable at $0.003 each, on or
before 31 December 2026
Performance Rights (Unlisted)
48,571,429 performance rights in
relation to acquisition of Gnows Nest
project
Directors:
Peter Thomas
Non-Executive Chairman
Terry Streeter
Non-Executive Director
Gavin Rutherford
Non-Executive Director
Tim Staermose
Non-Executive Director
Investor enquiries:
Doug Grewar CEO
M +61 419833604
E info@emunl.com.au
COMPETENT PERSON’S STATEMENT
The informa on in this report that relates to
explora on results is based on, and fairly represents
informa on and suppor ng documenta on prepared
by Kur s Dunstone, a Competent Person who is a
Member of the Australian Ins tute of Geoscien sts.
Mr Dunstone is an employee of EMU NL and has
sufficient experience in the ac vity which he is
undertaking to qualify as a Competent Person as
defined in the 2012 edi on of the “Australasian Code
for Repor ng of Explora on Results, Mineral
Resources and Ore Reserves”. Mr Dunstone consents
to the inclusion herein of the ma ers based upon his
informa on in the form and context in which it
appears.
FORWARD LOOKING STATEMENTS
As a result of a variety of risks, uncertain es and
other factors, actual events and results may differ
materially from any forward looking and other
statements herein not purpor ng to be of historical
fact. Any statements concerning mining reserves,
resources and explora on results are forward looking
in that they involve es mates based on assump ons.
Forward looking statements are based on
management’s beliefs, opinions and es mates as of
the respec ve dates they are made. The Company
does not assume any obliga on to update forward
looking statements even where beliefs, opinions and
es mates change or should do so given changed
circumstances and developments.
NEW INFORMATION OR DATA
EMU confirms that it is not aware of any new
informa on or data that materially affects the
informa on included in the original market
announcements and, in the case of es mates of
Mineral Resources, which all material assump ons
and technical parameters underpinning the es mates
in the relevant market announcement con nue to
apply and have not materially changed. The Company
confirms that the form and context in which the
Competent Person’s findings are presented have not
materially changed from the original market
announcement.
- END -
Page | 11
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
EMU NL
ABN
Quarter ended (“current quarter”)
50 127 291 927
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
31 December 2023
Current quarter
$A’000
Year to date
(6 months)
$A’000
-
-
(368)
(510)
(b) development
-
-
(c) production
-
-
(d) staff costs
(151)
(357)
(e) administration and corporate costs
(101)
(254)
(a) exploration & evaluation
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
5
11
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
-
-
1.9
Net cash from / (used in) operating
activities
(615)
(1,110)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
(58)
(c) property, plant and equipment
-
-
(d) exploration & evaluation
-
-
(e) investments
-
-
(f)
-
-
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date
(6 months)
$A’000
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
-
(58)
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
862
862
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(53)
(53)
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
-
-
3.10
Net cash from / (used in) financing
activities
809
809
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
596
1,149
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(615)
(1,110)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
-
(58)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
809
809
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(6 months)
$A’000
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
790
790
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
13
2
5.2
Call deposits
771
588
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
Cash deposit held in US$
6
6
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
790
596
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
53
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
-
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(615)
8.4
Cash and cash equivalents at quarter end (item 4.6)
790
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
790
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
1.28
(615)
-
-
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: EMU expects that it will continue to have negative operating cash flows as is usual
for mining exploration entities, but expenditures on discretionary exploration
expenses have been significantly curtailed and will be dependent on available cash
resources. The Company is rationalising its tenement holdings consistent with its
perception of market support/lack of support therefor.
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: The Company is considering opportunities to raise equity funding and/or the trade
sale of one or more tenements.
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: EMU expects to be able to continue its operations and meet its business objectives
based on its responses to 8.8.1 and 8.8.2 above.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
31 January 2024
Authorised by: Doug Grewar - CEO
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclo