Chile Gold Project Update and Drilling Approval
Released
Released
Announcement PDF
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
HIGHLIGHTS
VIDALITA GOLD PROJECT - NORTHERN CHILE
Ø January surface sampling confirms indications of gold mineralisation from the
December program with the soil results a major advance over the prospecting
work
Ø Evidence of gold mineralisation and anomalous geochemistry defined over a
large area of ~6km2
Ø IP survey completed and low resistivity target defined coincident with surface
geochemistry
Ø Targets being readied for drilling as drilling application granted
JOTAHUES GOLD PROJECT
Ø Surface prospecting locates zone of prytic alteration with gold geochemistry
CORPORATE
Ø Notices advising shareholders of the expiry of the 30th March 2017 options have
been dispatched
Ø The shareholders’ meeting held on 8th February 2017 passed all six resolutions
VIDALITA GOLD PROJECT
The Vidalita and nearby Jotahues gold projects are greenfields exploration projects and,
while the source of the surface evidence of mineralisation can only be speculation at this
stage, it is likely to be similar to known epithermal style gold ore deposits in the same
geological setting.
Surface Geochemical Results
During January, further surface samples were collected by Emu from Vidalita. Results
confirmed and extended previous results (Figures 1, 2, 3).
While the relationship between the surface results and any mineralisation is as yet unknown,
the geochemistry defines broadly two main domains – a western zone defined by gold, silver,
base metals and mercury; an eastern zone mainly defined by gold but still highly anomalous
in silver.
The high sulphidation systems of the Maricunga Belt in Chile are typically not uniformly
mineralised and often show geochemical zonation in space (vertically as a result of different
regimes of pressure and temperature) and time (different events as the system evolves). The
geochemical ‘assemblage’ of the western zone exhibits elements typically seen in many
epithemal systems. While the surface geochemistry suggests these elements may be absent in
the eastern zone, this does not downgrade that zone – it may be associated with an earlier or
later event and be gold/silver dominant.
Drilling
The work to date has not defined the limits to the geochemical and geological evidence of
mineralisation. While this phase of work is incomplete, Emu has elected to initiate a
drilling program in the current field season - which effectively ends at the end of May or
in some years, earlier - to obtain some sub-surface information in the areas delineated by the
work to date.
1
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
The task before the Company is to prioritise the drill targets as the evidence of mineralisation
is widespread. There is the possibility of the mineralisation being offset from the surface
geochemistry due to its original deposition and/or as a result of the redistribution caused by
subsequent landform events. The current plan is to test the most promising of the current
geochemical targets and to attempt to have at least one hole penetrate the resistivity target.
The Company has invited several drilling contractors to site to enable them to quote on the
drilling program. As this will be the first drilling program on Vidalita, the conditions are
unknown. For this reason, it is likely that this first program will be done using diamond
drilling to avoid problems with ground water and to obtain core.
Several drill targets have been defined and up to four of which may be tested depending on
drilling progress:
A (western zone) – this target is defined by high levels of gold, silver, base metals and
mercury. The target is open to the west and additional work is planned to close off the target
area. Rock samples returning grades up to 5.71 g/t gold and ~ 0.5oz/t silver have been
returned from this target.
B (eastern zone) – this is an extensive target area defined by gold (rock samples 1.23g/t) and
silver. It has low levels of base metals and mercury and is possible evidence of zonation of
the mineralising system.
C (central zone) – this target is defined by numerous rock chip results which returned up to
14.5 g/t gold and > 3oz/t silver and anomalous base metals and mercury.
D (northern zone) – this is a new zone located during January 2017. Rock samples showing
epithermal sinter textures returned gold values to 8.98g/t gold, > 3oz/t silver, 1040ppm
bismuth and 2.19% mercury. It is interpreted as a possible extension of the system in the
direction of the main structural lineaments of the district.
The drilling application has been approved and subject to satisfactory contract arrangements
being obtained, drilling is likely to commence this month.
Geology, Alteration and Geochronology
The Vidalita and Jotahues gold projects are located in the mineral rich, high sulphidation,
epithermal and gold porphyry Maricunga Belt of Chile. Late Paleozoic granitoids and lowgrade metamorphic units with epidote veins and weak chlorite alteration form the basement
to a thick Cenozoic volcanic and volcaniclastic sequence.
The oldest tertiary rocks recognized within the project area are andesitic flows and breccias
that can be correlated to the late Eocene to Oligocene Astaburuaga Formation. These
andesites are in general, weakly altered. Near the contact with younger intrusive rocks, the
andesite shows moderate to intense oxidation as well as argillic alteration features.
A series of discrete outcrops as well as sub-crops of dacitic rocks characterized by
plagioclase, biotite and amphibole phenochrysts >2mm ± quartz, glassy ground-mass and
flow-banding represent a second volcanic unit. Weak argillic to propillitic alteration
assemblages overprint the original mineralogy. An Oligocene to early-Miocene age is
tentatively assigned to these dacites.
Quartz-alunite alteration zones with vuggy silica and hydrothermal breccias, hosted by
andesitic lava flows or an andesitic flow dome have been observed at several locations within
the concessions. These quartz-alunite mineral assemblages are typical of high sulphidation
epithermal systems.
2
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
Potassium/argon dating of the alunite has given a date of 21.3 +/- 3.5my +/- which is
consistent with other dates from mineral deposits in the belt.
Alunite morphology: at least 3 types of alunite alteration have been identified. Massive pink
alunite is dominant in the southeastern zone (B), whereas tabular or bladed tan colored
crystals are found in the southwestern zone (A). Finally, porcellaneous masses (fine
pseudocubic crystals in amorphous silica groundmass) with replacement textures were
identified in the central area (C) where rocks with variable sinter-like textures of lowtemperature silica precipitation are observed.
The age dating is from material contained in the tabular or bladed tan colored crystals of
alunite. These are interpreted as high-sulfidation related, most likely formed in the 200 to 300
degrees C range.
Induced Polarisation Survey
The IP survey, commenced around 9th January, has been completed. The survey was
conducted using pole – dipole array and 100m dipoles (see Table 1 for other information).
Lines being surveyed were spaced every 400m and coincide with the surface geochemical
sampling lines.
The inversion results show a large, flat, low resistivity zone below and coincident with the
surface geochemistry (figure 4). Mapping has not provided an explanation for the cause of
this feature as the area is interpreted to be underlain by volcanics, intrusives and minor
hornfelsed sediments. Possible, and, significantly, encouraging causes consistent with the
extensive surface geochemistry and evidence of epithermal mineralisation is a large zone of
increased porosity and/or alteration associated with the mineralising event.
JOTAHUES GOLD PROJECT
Limited surface prospecting in the northern most concession has located an area of pyritic
minerlaisation within altered volcanics. Samples of this material returned gold asssays to
0.287 g/t.
NOTICE OF OPTION EXPIRY
Notices advising shareholders of the expiry of their 30th March 2017 options were dispatched
on 21st February 2017.
SHAREHOLDERS’ MEETING
The shareholders’ meeting on 8th February 2017 passed all resolutions. The shareholder
approvals received at this meeting satisfied the last condition precedent to the option
agreement for project acquisition between Emu, Prospex SpA and BLC SpA. The first
tranche of Emu shares (2.5 million) have been allotted to Propspex in accordance with the
agreement.
WEBSITE
The Company’s website has been subject to attack recently rendering it difficult to use. The
Company has engaged a website designer to construct a new website and which should be
operational this month.
1st March 2017
For more information on the company visit www.emunl.com.au
3
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
D
C
A
B
Figure 1
4
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
Figure 2
5
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
Figure 3
6
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
Figure 4 Induced Polarisation Results and Inversion
7
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
ABOUT THE CHILE GOLD PROJECTS
The Vidalita and Jotahues gold projects are located in the highly mineralised
Oligocene/Miocene Maricunga gold belt in northern Chile, approximately 200 km east from
the city of Copiapó in the Atacama Region of Chile. The two projects cover an area of
approximately 3,600 hectares of mineral exploration concessions and hosts alteration and
mineralization that appears geologically similar to other high sulphidation oxide gold
deposits of the Maricunga gold belt. The projects are accessed using a network of roads that
link Copiapó with the Refugio project (Kinross), Cerro Casale project (Barrick/Kinross) and
the Caspiche project (Exeter). Refugio is located 30 km to the northwest of Vidalita. No
known previous exploration has occurred on the project.
CHILE GOLD EXPLORATION
MARICUNGA BELT DEPOSITS
Salares Norte (Gold Fields) - Inferred Resource of
23.3 Mt @ 4.2 g/t Au & 44 g/t Ag, for 3.1 Moz Au &
34 Moz Ag
Maricunga Mine (Kinross ) - 390 Mt @ 0.7 g/t Au
Cerro Casale (Barrick/Kinross) - 1,200 Mt @ 0.6 g/t
Au
Cerro Maricunga Mine (Atacama Pacific) - 473 Mt @
0.4 g/t Au
Caspiche project (Exeter ) - 810 Mt @ 0.67 g/t Au
Alturas (Barrick) - 5.5M oz @ 1.25 g/t; intercepts of
170 meters grading 2.76 g/t Au
Emu has an option agreement with Prospex SpA and BLC SpA, Chilean subsidiaries of
Altius Minerals Corporation of Canada, to acquire 11 concessions at Vidalita and 3
concessions at Jotahues. This option maybe exercised any time up until November 2019 by
granting Prospex and BLC a 1% NSR on production and allotting them up to 15 million Emu
ordinary shares subject to certain vesting conditions (see ASX release 15th November 2016).
Prospex SpA in turn has an option to acquire 6 of the 11 Vidalita concessions from local
Chilean parties. Under the terms of that agreement, Prospex has the right to exercise that
option by November 2019 by paying US$2 million and granting the Chilean parties a 1%
NSR over those 6 concessions. Under the Emu option agreement, Emu has assumed the rights
and obligations of Prospex in relation to those 6 concessions.
8
CHILE GOLD PROJECT UPDATE
AND
DRILLING APPROVAL
EMU NL ABN 50 127 291 927
COMPETENT PERSON’S STATEMENT
Emu NL
ABN 50 127 291 927
ASX Code: EMU
10 Walker Ave
West Perth, WA 6005
T +61 8 9226 4266
E info@emunl.com.au
PO Box 1112
West Perth, WA 6872
The details contained in this report that pertain to exploration
results, mineral resources and mineral reserves are based upon
information compiled by Mr. Greg Steemson, Managing
Director of Emu NL. Mr. Steemson is a Fellow of the
Australasian Institute of Mining and Metallurgy (FAusIMM)
and has sufficient experience in the activity which he is
undertaking to qualify as a Competent Person as defined in
the 2012 edition of the “Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves”
(JORC Code). Mr. Steemson consents to the inclusion in the
report of the matters based upon his information in the form
and context in which it appears.
Issued Capital:
Quoted:
Shares
44,886,525 fully paid shares
Contributing Shares
33,679,246 paid to $0.03; $0.03
to pay, no call before
31/12/2017
Unlisted Options
14,550,283 options, exercise
price $0.10, date 30/3/17
Directors:
Peter Thomas
Chairman
Greg Steemson
Managing Director
Gavin Rutherford NonExecutive Director
FORWARD LOOKING STATEMENT
This report contains forward looking statements concerning
the projects owned by Emu NL. Statements concerning
mining reserves, resources and exploration results may also
be deemed to be forward looking statements in that they
involve estimates based on specific assumptions. Forwardlooking statements are not statements of historical fact and
actual events and results may differ materially from those
described in the forward looking statements as a result of a
variety of risks, uncertainties and other factors. Forward
looking statements are based on management’s beliefs,
opinions and estimates as of the dates the forward looking
statements are made and no obligation is assumed to update
forward looking statements if these beliefs, opinions and
estimates should change or to reflect other future
developments.
9
JORC Code, 2012 Edition – Table 1 report, EMU NL
Vidalita soil sampling & Induced Polarisation results
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria
Explanation
Commentary
Sampling
techniques
Nature and quality of sampling (eg cut
channels, random chips, or specific
specialised industry standard measurement
tools appropriate to the minerals under
investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc).
These examples should not be taken as
limiting the broad meaning of sampling.
Surface sampling technique taking
~ 2 kg of -6mm material every
50m along lines oriented east –
west and spaced 400m or 200m
apart.
Three hundred and seventy six
(367) samples were collected in
the December and January
programs.
Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any measurement
tools or systems used.
Aspects of the determination of
mineralisation that are Material to the Public
Report. In cases where ‘industry standard’
work has been done this would be relatively
simple (eg ‘reverse circulation drilling was
used to obtain 1 m samples from which 3 kg
was pulverised to produce a 30 g charge for
fire assay’). In other cases more explanation
may be required, such as where there is
coarse gold that has inherent sampling
problems. Unusual commodities or
mineralisation types (eg submarine nodules)
may warrant disclosure of detailed
information.
Each sample was dried and
screened to +2mm split to produce
~250gm for pulverizing.
Each fraction was pulverized
separately 85% passing
75microns.
50gm from each sample was
digested using aqua regia and
analysed for a range of elements
using method Au-ME-ST44 (50
gm) using ICP-MS.
Elements analysed for include
gold, silver, arsenic, base metals
and mercury.
One hundred and sixty four rock
samples have been collected from
Vidalita area. Samples were sent
to Copiapo for 30g fire assay and
four acid digest ICP anlysis +
mercury.
Drilling
techniques
Drill type (eg core, reverse circulation, openhole hammer, rotary air blast, auger,
Bangka, sonic, etc) and details (eg core
diameter, triple or standard tube, depth of
diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by
No drilling done.
what method, etc).
Drill sample
recovery
Method of recording and assessing core and
chip sample recoveries and results assessed.
Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
Whether a relationship exists between sample
recovery and grade and whether sample bias
may have occurred due to preferential
loss/gain of fine/coarse material.
Logging
Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
Whether logging is qualitative or quantitative
in nature. Core (or costean, channel, etc)
photography.
The total length and percentage of the
relevant intersections logged.
Sub-sampling
techniques and
sample
preparation
If core, whether cut or sawn and whether
quarter, half or all core taken.
If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet or
dry.
For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
Quality control procedures adopted for all
sub-sampling stages to maximise
representivity of samples.
Measures taken to ensure that the sampling is
The area sampled is typical of
representative of the in situ material
peri-glacial areas and as such
collected, including for instance results for
outcrop can be sparse. The soils
field duplicate/second-half sampling.
are best described as colluvial.
Sampling was done to avoid
Whether sample sizes are appropriate to the
obvious alluvial sediments.
grain size of the material being sampled.
Quality of
assay data and
The nature, quality and appropriateness of
the assaying and laboratory procedures used
The laboratory assayed 1:10
duplicate samples, standard
laboratory tests
and whether the technique is considered
partial or total.
samples and blanks.
For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the analysis
including instrument make and model,
reading times, calibrations factors applied
and their derivation, etc.
Nature of quality control procedures adopted
(eg standards, blanks, duplicates, external
laboratory checks) and whether acceptable
levels of accuracy (ie lack of bias) and
precision have been established.
Verification of
sampling and
assaying
The verification of significant intersections by
either independent or alternative company
personnel.
The use of twinned holes.
Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
Discuss any adjustment to assay data.
Location of
data points
Accuracy and quality of surveys used to
locate drill holes (collar and down-hole
surveys), trenches, mine workings and other
locations used in Mineral Resource
estimation.
Specification of the grid system used. s
Quality and adequacy of topographic control.
Data spacing
Data spacing for reporting of Exploration
and distribution Results.
Whether the data spacing and distribution is
sufficient to establish the degree of
geological and grade continuity appropriate
for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications
applied.
Whether sample compositing has been
applied.
Sample points were located using
hand held GPS accurate to < 5m.
Orientation of
data in relation
to geological
structure
Whether the orientation of sampling achieves
unbiased sampling of possible structures and
the extent to which this is known, considering
the deposit type.
The sampling density would be
sufficient to achieve an unbiased
result.
If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
Sample security
The measures taken to ensure sample
security.
Audits or
reviews
The results of any audits or reviews of
sampling techniques and data.
None undertaken.
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria
Explanation
Commentary
Mineral
tenement and
land tenure
status
Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint
ventures, partnerships, overriding royalties,
native title interests, historical sites,
wilderness or national park and
environmental settings.
Emu has an option agreement with
Prospex SpA and BLC SpA,
Chilean subsidiaries of Altius
Minerals Corporation of Canada,
to acquire 11 concessions at
Vidalita and 3 concessions at
Jotahues. This option maybe
exercised any time up until
November 2019 by granting
Prospex and BLC a 1% NSR on
production and allotting them up
to 15 million Emu ordinary shares
subject to certain vesting
conditions (see ASX release 15th
November 2016). Prospex SpA in
turn has an option to acquire 6 of
the 11 Vidalita concessions from
local Chilean parties. Under the
terms of that agreement, Prospex
has the right to exercise that option
by November 2019 by paying
US$2 million and granting the
Chilean parties a 1% NSR over
those 6 concessions. Under the
Emu option agreement, Emu has
assumed the rights and obligations
The security of the tenure held at the time of
reporting along with any known
impediments to obtaining a licence to
operate in the area.
of Prospex in relation to those 6
concessions.
Exploration
done by other
parties
Acknowledgment and appraisal of
exploration by other parties.
Geology
Deposit type, geological setting and style of
mineralisation.
Drill hole
Information
A summary of all information material to the
understanding of the exploration results
including a tabulation of the following
information for all Material drill holes:
The project is a green fields
exploration project and while the
source of the surface evidence of
mineralization can only be
speculation at this stage, it is likely
to be similar to known epithermal
style ore deposits in the same
geological setting.
easting and northing of the drill hole
collar
elevation or RL (Reduced Level – elevation
above sea level in metres) of the drill hole
collar
dip and azimuth of the hole s down hole
length and interception depth s hole length.
If the exclusion of this information is
justified on the basis that the information is
not Material and this exclusion does not
detract from the understanding of the report,
the Competent Person should clearly
explain why this is the case.
Data
aggregation
methods
In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (eg cutting of
high grades) and cut-off grades are usually
Material and should be stated.
Where aggregate intercepts incorporate
short lengths of high grade results and
longer lengths of low grade results, the
procedure used for such aggregation should
be stated and some typical examples of such
aggregations should be shown in detail.
No aggregation undertaken.
The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
Relationship
between
mineralisation
widths and
intercept lengths
These relationships are particularly
important in the reporting of Exploration
Results.
Project is at an early stage of
exploration and any conclusions at
this stage would be speculation.
If the geometry of the mineralisation with
respect to the drill hole angle is known, its
nature should be reported.
If it is not known and only the down hole
lengths are reported, there should be a clear
statement to this effect (eg ‘down hole
length, true width not known’).
Diagrams
Appropriate maps and sections (with scales)
and tabulations of intercepts should be
included for any significant discovery being
reported. These should include, but not be
limited to a plan view of drill hole collar
locations and appropriate sectional views.
Balanced
reporting
Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and
high grades and/or widths should be
practiced to avoid misleading reporting of
Exploration Results.
Other
substantive
exploration data
Other exploration data, if meaningful and
material, should be reported including (but
not limited to): geological observations;
geophysical survey results; geochemical
survey results; bulk samples – size and
method of treatment; metallurgical test
results; bulk density, groundwater,
geotechnical and rock characteristics;
potential deleterious or contaminating
substances.
Further work
The nature and scale of planned further
work (eg tests for lateral extensions or depth
The IP survey was done by
Quantec Geoscience Limited of
Canada.
Receiver – Iris Instruments Elrec
Pro
Transmitter – Iris Instruments VIP
10000
Duty cycle – 2 sec on/off
Potential electrodes – stainless
steel rods
Current electrodes – foil
Array – pole-dipole
Dipole length – 100m
N spacing – to N=10 depending on
signal strength
extensions or large-scale step-out drilling).
Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future
drilling areas, provided this information is
not commercially sensitive.