SPEEDWAY GOLD PROJECT, USA
SPDRCD1 CORE ASSAY RESULTS
SPDRCD1 CORE ASSAY RESULTS
Gold assay results have been received for the cored section of SPDRCD1. While there is
detectable gold in the assays received, the gold values are < 0.1ppm.
The Company has elected not to proceed with drilling the second hole at this time.
10TH MARCH 2016
For more information on the company visit www.emunl.com.au
ABOUT SPEEDWAY
The Speedway Project was generated by Don Merrick and John Zimmerman of Genesis Gold
Corporation, a private Utah company specializing in gold exploration in the Western United
States.
1
EMU NL ABN 50 127 291 927
SPEEDWAY GOLD PROJECT, USA
SPDRCD1 CORE ASSAY RESULTS
Emu NL
ABN 50 127 291 927
ASX Code: EMU
10 Walker Ave
West Perth, WA 6005
T +61 8 9226 4266
E info@emunl.com.au
PO Box 1112
West Perth, WA 6872
Issued Capital:
Quoted:
Shares
40,233,493 fully paid shares
Contributing Shares
35,324,341; paid to $0.03;
$0.03 to pay, no call before
31/12/2017
Unlisted Options:
15,058,220 options, exercise
price $0.10, date 30/3/17
Directors:
Peter Thomas
Chairman
Greg Steemson
Managing Director
Gavin Rutherford NonExecutive Director
COMPETENT PERSON’S STATEMENT
The details contained in this report that pertain to exploration
results, mineral resources and mineral reserves are based upon
information compiled by Mr. Greg Steemson, Managing
Director of Emu NL. Mr. Steemson is a Fellow of the
Australasian Institute of Mining and Metallurgy (FAusIMM)
and has sufficient experience in the activity which he is
undertaking to qualify as a Competent Person as defined in
the 2012 edition of the “Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves”
(JORC Code). Mr. Steemson consents to the inclusion in the
report of the matters based upon his information in the form
and context in which it appears.
FORWARD LOOKING STATEMENT
This report contains forward looking statements concerning
the projects owned by Emu NL. Statements concerning
mining reserves and resources may also be deemed to be
forward looking statements in that they involve estimates
based on specific assumptions. Forward-looking statements
are not statements of historical fact and actual events and
results may differ materially from those described in the
forward looking statements as a result of a variety of risks,
uncertainties and other factors. Forward looking statements
are based on management’s beliefs, opinions and estimates as
of the dates the forward looking statements are made and no
obligation is assumed to update forward looking statements if
these beliefs, opinions and estimates should change or to
reflect other future developments.
2
JORC Code, 2012 Edition – Table 1 report, EMU NL
SPDRCD1 – Diamond Drilling Results February 2016
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria
Explanation
Commentary
Sampling
techniques
Nature and quality of sampling (eg cut
channels, random chips, or specific
specialised industry standard measurement
tools appropriate to the minerals under
investigation, such as down hole gamma
sondes, or handheld XRF instruments, etc).
These examples should not be taken as
limiting the broad meaning of sampling.
The HQ core was marked up into
nominal 5 feet sections for cutting
into halves. One half was bagged
for assay. The core was crushed to
2mm and 250g split for
pulverising.
Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any measurement
tools or systems used.
Aspects of the determination of
mineralisation that are Material to the Public
Report. In cases where ‘industry standard’
work has been done this would be relatively
simple (eg ‘reverse circulation drilling was
used to obtain 1 m samples from which 3 kg
was pulverised to produce a 30 g charge for
fire assay’). In other cases more explanation
may be required, such as where there is
coarse gold that has inherent sampling
problems. Unusual commodities or
mineralisation types (eg submarine nodules)
may warrant disclosure of detailed
information.
The laboratory then sub-sampled
the pulverized sample to produce a
30g for fire assay AA finish and
1g for aqua regia digest for multi
element assay.
Duplicate composite samples were
submitted for analysis.
Drilling
techniques
Drill type (eg core, reverse circulation, openhole hammer, rotary air blast, auger,
Bangka, sonic, etc) and details (eg core
diameter, triple or standard tube, depth of
diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by
what method, etc).
Core drilling using HQ size bit.
Drill sample
recovery
Method of recording and assessing core and
chip sample recoveries and results assessed.
Core recovery was > 95%.
Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
Whether a relationship exists between sample
recovery and grade and whether sample bias
may have occurred due to preferential
loss/gain of fine/coarse material.
Logging
Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
Core was geologically logged.
Whether logging is qualitative or quantitative
in nature. Core (or costean, channel, etc)
photography.
The total length and percentage of the
relevant intersections logged.
Sub-sampling
techniques and
sample
preparation
If core, whether cut or sawn and whether
quarter, half or all core taken.
Core was sawn into halves and one
half bagged for analysis.
If non-core, whether riffled, tube sampled,
rotary split, etc and whether sampled wet or
dry.
For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
Quality control procedures adopted for all
sub-sampling stages to maximise
representivity of samples.
Measures taken to ensure that the sampling is
representative of the in situ material
collected, including for instance results for
field duplicate/second-half sampling.
Whether sample sizes are appropriate to the
grain size of the material being sampled.
Quality of
assay data and
laboratory tests
The nature, quality and appropriateness of
the assaying and laboratory procedures used
and whether the technique is considered
partial or total.
For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the analysis
The core was assayed using a 30g
charge for fire assay.
including instrument make and model,
reading times, calibrations factors applied
and their derivation, etc.
Nature of quality control procedures adopted
(eg standards, blanks, duplicates, external
laboratory checks) and whether acceptable
levels of accuracy (ie lack of bias) and
precision have been established.
Verification of
sampling and
assaying
The laboratory used standards and
blanks as part of the QA/QC
1 in 10 duplicates were collected
for analysis.
The verification of significant intersections by No significant results were
either independent or alternative company
returned.
personnel.
The use of twinned holes.
Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
Discuss any adjustment to assay data.
Location of
data points
Accuracy and quality of surveys used to
locate drill holes (collar and down-hole
surveys), trenches, mine workings and other
locations used in Mineral Resource
estimation.
Specification of the grid system used. Quality
and adequacy of topographic control.
The hole collar was established
using a hand held GPS instrument
and is accurate to +/- 3m.
251376E 4524328N
UTM WGS 84
Data spacing
Data spacing for reporting of Exploration
and distribution Results.
Whether the data spacing and distribution is
sufficient to establish the degree of
geological and grade continuity appropriate
for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications
applied.
Whether sample compositing has been
applied.
Orientation of
data in relation
to geological
structure
Whether the orientation of sampling achieves
unbiased sampling of possible structures and
the extent to which this is known, considering
the deposit type.
If the relationship between the drilling
Yes
orientation and the orientation of key
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
No
Sample security
The measures taken to ensure sample
security.
A company director was on site
for the duration of the program.
Audits or
reviews
The results of any audits or reviews of
sampling techniques and data.
None done
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria
Explanation
Commentary
Mineral
tenement and
land tenure
status
Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint
ventures, partnerships, overriding royalties,
native title interests, historical sites,
wilderness or national park and
environmental settings.
The Speedway mineral claims are
owned by Steamship Copper and
Gold, LLC. American Emu Inc.
has an agreement with Genesis
whereby American Emu can
acquire 100% interest in the
claims subject to making certain
payments to Genesis and granting
Genesis a 2% NSR (details
announced to ASX 29th October
2015).
The claims are located on Bureau
of Land Management land.
The security of the tenure held at the time of
reporting along with any known
impediments to obtaining a licence to
operate in the area.
Exploration
done by other
parties
Acknowledgment and appraisal of
exploration by other parties.
Geology
Deposit type, geological setting and style of
mineralisation.
Drill hole
Information
A summary of all information material to the
understanding of the exploration results
including a tabulation of the following
information for all Material drill holes:
easting and northing of the drill hole collar
elevation or RL (Reduced Level – elevation
above sea level in metres) of the drill hole
The AMT data was collected by
Industrial Imaging Corporation.
SPDRCD1 UTM WGS 84
coordinates
251376E 4524328N
Dip vertical
Hole length 1,687 feet
collar
dip and azimuth of the holes down hole
length and interception dept s hole length.
If the exclusion of this information is
justified on the basis that the information is
not Material and this exclusion does not
detract from the understanding of the report,
the Competent Person should clearly explain
why this is the case.
Data
aggregation
methods
In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (eg cutting of
high grades) and cut-off grades are usually
Material and should be stated.
N/A
Where aggregate intercepts incorporate
short lengths of high grade results and
longer lengths of low grade results, the
procedure used for such aggregation should
be stated and some typical examples of such
aggregations should be shown in detail.
The assumptions used for any reporting of
metal equivalent values should be clearly
stated.
Relationship
between
mineralisation
widths and
intercept lengths
These relationships are particularly
important in the reporting of Exploration
Results.
If the geometry of the mineralisation with
respect to the drill hole angle is known, its
nature should be reported.
If it is not known and only the down hole
lengths are reported, there should be a clear
statement to this effect (eg ‘down hole
length, true width not known’).
Diagrams
Appropriate maps and sections (with scales)
and tabulations of intercepts should be
included for any significant discovery being
reported. These should include, but not be
limited to a plan view of drill hole collar
locations and appropriate sectional views.
N/A
Balanced
reporting
Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and
high grades and/or widths should be
practiced to avoid misleading reporting of
Exploration Results.
Other
substantive
exploration data
Other exploration data, if meaningful and
material, should be reported including (but
not limited to): geological observations;
geophysical survey results; geochemical
survey results; bulk samples – size and
method of treatment; metallurgical test
results; bulk density, groundwater,
geotechnical and rock characteristics;
potential deleterious or contaminating
substances.
Further work
The nature and scale of planned further
work (eg tests for lateral extensions or depth
extensions or large-scale step-out drilling).
Diagrams clearly highlighting the areas of
possible extensions, including the main
geological interpretations and future drilling
areas, provided this information is not
commercially sensitive.
N/A
Share your feedback
Discover